Start New Real Estate File
Thanks for voting us as your favourite law firm for 2023!
- TriCity News
Good advice.

Good advice.

What is a Builders Lien Holdback?

DBM Law Blog

Both the holdback and the power to lien come from the Builders Lien Act (the “Act”).  The purpose of the act is twofold:

  • To provide security for contractors and subcontractors who work on a construction project
  • To limit the owner of a properties liability

The Act requires all persons on a project to retain 10% from all amounts paid for the work done on the project.  This 10% holdback has nothing to do with deficiencies, delay claims, or other potential liabilities that a contractor or subcontractor may suffer. In fact, many construction contracts will include further holdback amounts for items like potential deficiencies.  The 10% builders lien holdback is not related to your contract and you cannot contract out of that requirement.

Any contractor or subcontractor must holdback 10% of the contract price until the end of the holdback period.  It is important to note that you do not holdback back funds from workers, material suppliers, architects or engineers.

When is the holdback money paid?

The holdback requirement exists so there is money available if a contractor or subcontractor is not paid and places a lien on the property on which the project is being worked.  To that extent, it also limits the liability of an owner or contractor who is required to retain a holdback.  Their liability under a lien is capped at the amount of holdback required.  A contractor or subcontractor seeking more than that amount would need to pursue it outside the lien (i.e. through a debt claim in small claims or Supreme Court).

Because the holdback exists to satisfy possible lien claimants, the holdback period is directly tied to the lien period.  The lien period starts to run 45 days after the earliest of the following events occurs:

  1. completion of the head contract, or, if there is no head contract, substantial completion of the project;
  2. termination of the head contract before a certificate of completion has been issued;
  3. abandonment of the head contract before a certificate of completion has been issued.

Completion is defined in the act, and means ‘substantial completion’ of the project.  An owner or head contractor may apply for a certificate of completion, which will trigger the 45 day lien period.  If you, as a contractor or subcontractor, receive a certificate of completion, it means you have to act quickly to protect yourself if money (aside from the holdback amount) is still outstanding.

The holdback period begins to run at the same time as the lien period. It, however, expires after 55 days of the triggering event.  If no liens have been filed against the property, the holdback funds must be released at the end of the holdback period.  The holdback funds cannot be released prior to the 55 day mark.

If a lien is filed by any party, the holdback funds cannot be released until it is discharged.

Summary

It is mandatory that any contract holder on a project hold back 10% of the contract amount owed.  An owner will hold back 10% of the contract price from the head contractor.  The head contractor will hold back 10% from each subcontractor and so on down the chain.

The holdback exists to protect potential lien claimants.  As such, both the ‘lien period’ and ‘holdback period’ start at the same time (at completion, termination or abandonment of a project).  If someone is owed money on the project, then they may lien the property within 45 days of that triggering event.  If no one files a lien, then the holdback moneys may be released 10 days after that deadline.

The lawyers at Drysdale Bacon McStravick LLP are here to assist you if you are owed money on a project you worked on.

Categories

How Can We Help You Today?

(604) 939 8321